The cul-de-sac at the head of the west rows, with the building row along one side. This is the only permanent area: field office, bulk material laydown, the primary roll-offs and the equipment and lift pool sit here for the full 60 weeks.
Close-up taken from the site walk and carried on the Laydown & Staging Plan drawing. Aerial imagery, not a photograph of work in progress.
A parking court set back off the travel lane, with covered parking structures along it. Material and the dumpster stand on existing pavement, clear of the turf and the pond bank.
Close-up taken from the site walk and carried on the Laydown & Staging Plan drawing. Aerial imagery, not a photograph of work in progress.
Angled parking bays on the elbow of the interior drive, serving the central rows around the middle pond. The bays give a short carry to either side of the elbow.
Close-up taken from the site walk and carried on the Laydown & Staging Plan drawing. Aerial imagery, not a photograph of work in progress.
A straight run of parking bays along the interior drive with the kerb line and walk visible. The longest-serving of the rotating areas, carrying 22 buildings.
Close-up taken from the site walk and carried on the Laydown & Staging Plan drawing. Aerial imagery, not a photograph of work in progress.
A short parking strip between the drive and the building row. The tightest of the seven areas, so dumpster and material move building to building as the work walks the row.
Close-up taken from the site walk and carried on the Laydown & Staging Plan drawing. Aerial imagery, not a photograph of work in progress.
Parking bays on the connector road, occupied at the time of the site walk. Resident parking has to be worked around here, which is why the notice for this area names the spaces coming out of use.
Close-up taken from the site walk and carried on the Laydown & Staging Plan drawing. Aerial imagery, not a photograph of work in progress.
The cul-de-sac parking at the detached cluster, curving around the island. Four buildings only, and the last area to open.
Close-up taken from the site walk and carried on the Laydown & Staging Plan drawing. Aerial imagery, not a photograph of work in progress.
Contract deadline is 104 weeks from NTP (30 Oct 2028). This 60-week plan finishes 30 Dec 2027, leaving about 43 weeks of float.